2a23b30f83
chore: update STATE after Phase 04 multi-agent follow-up
2026-04-24 14:12:07 +03:00
430c82dba1
feat(04-01): finalize AgentApi migration
2026-04-17 16:31:48 +03:00
6923b801a3
wip: phase 4 planning complete, ready to execute
2026-04-17 15:36:19 +03:00
795a56c686
docs(01.1): capture matrix restart and reset phase context
2026-04-03 16:25:48 +03:00
fe096c51b7
docs(01-06): complete matrix gap-closure plan
...
Tasks completed: 2/2
- Remove reaction-era Matrix UX and strict !settings snapshot
- Harden room-vs-chat Matrix regressions
SUMMARY: .planning/phases/01-matrix-qa-polish/01-06-SUMMARY.md
2026-04-03 12:37:11 +03:00
80800be60c
docs(01-05): complete matrix confirmation scope plan
...
- add 01-05 summary with self-check results
- update planning state and roadmap progress for phase 01
2026-04-03 12:29:44 +03:00
0d85947a0b
docs(01-03): complete reaction removal plan
...
- add execution summary for Matrix text confirmation changes
- update state tracking and roadmap progress for phase 01
- record plan completion details for follow-up test work
2026-04-02 22:58:15 +03:00
4636b359e2
docs(01-02): complete matrix chat handlers plan
...
- record the 01-02 execution summary and self-check
- update roadmap progress for completed phase 01 plans
- persist state decisions, metrics, and next-plan focus
2026-04-02 22:53:07 +03:00
3130ed3095
chore: initialize GSD planning structure (PROJECT, ROADMAP, STATE, config)
2026-04-02 17:29:43 +03:00